all projects
Description:
TPS have worked with Balvac (a subsidiary of Balfour Beatty) to complete the compound set-ups and decommissioning associated with Various Bridge repair projects.
Subcontract works:
TPS have installed compounds for Balvac at Peover, Barton, Uttoxeter and Dorchester – all varying in size and with different TM constraints.
TPS scope of works included the following:
- Site clearance
- Removal / treatment of invasive species
- Topsoil strip
- Earthworks cut / fill
- Supply and install geotextiles
- Supply and install geogrids
- Supply and installation Type 1 MOT
- Disposal of MOT on completion of the works
- Reinstatement of topsoil / grass seeding
Employer: Various
Main Contractor: Balvac
Form of Subcontract: NEC3 Option B
Value: £250k (combined)